Efficient solutions from NETZER GROUP always keep an eye on costs

The NETZER GROUP installed a certified BUS system to control the mechanical fire smoke dilution system in the new baking lines for toast and plaited bread at ÖLZ der Meisterbäcker. This implementation alone significantly reduced acquisition and maintenance costs. Overall, the planning and implementation of the project was a challenge, especially the coordination of the building technology with the requirements of the system technology, which was supplied by various companies from all over Europe.

In view of the complexity and the large number of technical infrastructures, the NETZER GROUP project team opted for collaborative 3D planning. This ensured a smooth construction process and adherence to deadlines, as well as minimizing additional costs due to changes, for example. Professional cost management contributes to the cost-effectiveness of the project and shows how state-of-the-art technology can be used sustainably and cost-effectively.

Facts_Oelz-Meisterbaecker

Factbox

Responsibility:
Planning, project management and production supervision of technical building equipment
Implementation time:
3.5 years from planning to start of production
room area:

Production 2.500m²
High-bay warehouse & order picking 2,800m²
Materials management 4.500m²
Administration 950m²
Social rooms 1.000m²
Underground parking garage 3.700m²
Clean rooms 1.500m²
Technical rooms 3.600m²
ancillary rooms 10.500m²

Trades:

Heating
Cooling
Steam
Compressed air
Sanitation
Ventilation
I&C technology