Info
Project
Adaptation of ventilation
Construction time
1st construction phase 2017 - 2nd construction phase 2018
Description
The company 11er Nahrungsmittel GmbH replaced all of the air conditioning systems in its production facilities. At the same time, 1 MW of heating energy was decoupled from the chillers as an energy-saving measure.
Technical data
16 ventilation systems
Total air volume: 400,000 m³/h
Central heat supply ventilation: 3 MW
Heat recovery chiller: 1 MW
Concrete core activation: 2,500 m²
Heating/cooling ceiling: 200 m²
Special features
The work in production, such as the ductwork, could only be carried out during the 3 weeks of company vacation. This made it a challenge to coordinate all the trades.