FLATZ GMBH, LAUTERACH

Info

Project
Shipping and high-bay warehouse
Construction time
2016-2017
Description
Due to the company's continued success, Flatz needs to improve its own infrastructure. By building a new logistics center with a fully automated high-bay warehouse 4, the company sets new standards in flexibility, speed and delivery service.
Technical data
HRL: Building height 34.9 m / 16,200 and 5 RBGs HRL ventilation unit 8,00 m³/h Dispatch building: 14 loading ramps Ventilation unit with 12,700 m³/h and a heating heating capacity of 170 kW Compressor WRG 42 kW Radiant ceiling panels 145 kW Air curtain system 240 kW
Special features
A sprinkler system with 16,000 sprinklers is installed throughout the new building. Smoke extraction system in the dispatch building with 40,000 m³/h The piping and positioning of the individual sprinklers at the pallet storage areas in the HBW were a particular challenge.