LAND-LEBEN FOOD GMBH, ANTHERING

Info

Projects
New production
construction time
2015 - 2016
Description
Traditional company for the production of soups and salads from Salzburg. Frying and drying processes with thermal oil. Heat supply almost exclusively via waste heat from the production processes. The adsorption chiller is operated with waste heat, the chiller with dry cooler and free cooling function.
Technical data
Thermal oil boiler: 2100 kW (VL 264°C) Total air volume: 92.000 m³/h Adsorption chiller: 139 kW HR air compressor: 36 kW HR thermal oil: 185 kW Component activation: 5000 m² heat pump Boiler house cooling: 40 kW Free cooling: 488 kW
Features
Since the project was around 350 km away from the company site, very detailed execution planning was necessary to enable efficient construction management. Short execution phase of approx. 8 months from start to commissioning.