LAND-LEBEN NAHRUNGSMITTEL GMBH, ANTHERING

Info

Project
New production building
Construction time
2015 - 2016
Description
Traditional company for the production of soups and salad dressings from Salzburg. Deep-frying and drying processes with thermal oil. Heat supply almost exclusively via waste heat from the production processes. Adsorption chiller is operated with waste heat, the chiller with recooler and free cooling function.
Technical data
Thermal oil boiler: 2100 kW (VL 264°C) Total air volume: 92,000 m³/h Adsorption chiller: 139 kW WRG air compressor: 36 kW WRG thermal oil: 185 kW Building component activation: 5000 m² Boiler house cooling heat pump: 40 kW Free cooling: 488 kW
Special features
As the project was approx. 350 km away from the company's location, very detailed implementation planning was necessary to enable efficient construction management. Short execution phase of approx. 8 months from start to commissioning.